The BMO Centre at Stampede Park is one of Canada’s largest and most complex convention venues. With the completion of its $500 million expansion in June 2024, the facility now spans over one million square feet across three levels — encompassing expansive exhibition halls, multi-level ballrooms, meeting rooms, and pre-function spaces. Recognizing that a venue of this scale demanded purpose-built, carrier-grade wireless infrastructure, the carrier engaged Pillar Telecom to deliver an active DAS solution with the density and precision to serve tens of thousands of concurrent users.
The scale of the installation presented significant logistical complexity. Cable routes, equipment placement, and crew scheduling had to be tightly coordinated across all three levels of a fully finished, high-quality interior environment — with zero tolerance for damage to completed finishes and strict access controls in place throughout the venue.
The BMO Centre had only recently completed its expansion phase when the carrier engaged Pillar to begin the DAS installation, meaning the work was carried out within a multi-contractor environment with active handover processes underway. All work had to meet the carrier’s stringent commissioning and acceptance standards — with no margin for error on a project of this profile.
Engaged to deliver a complete end-to-end turnkey scope across the full BMO Centre footprint, Pillar Telecom executed every phase of the installation. The scope of work included:
Antenna Mount Supply and Installation — Supply and installation of all antenna mounts throughout the building, positioned to achieve the required coverage density across all zones. For maximum aesthetics, mounts were colour matched and painted before installation.
Cabling Infrastructure — Supply and installation of hybrid cabling throughout the building, forming the structured backbone of the active DAS network.
Remote Unit Deployment — Precise placement and connection of 70 N2/N3 remote units distributed throughout the venue across all three levels.
Commissioning and Handover — Complete system commissioning and handover to the carrier, with all 70 remote units live and the full DAS network meeting carrier acceptance standards upon completion.
Pillar self-performed all phases of the installation, managing the full project lifecycle — from initial planning through to final commissioning — coordinating crew scheduling and equipment logistics across one million square feet of finished interior space.